There is plenty developing at our Wesley communities. It’s time to get caught up on all the updates.
Wesley Bradley Park: East Brownstone
The East Brownstone is entering its final month of construction, with move-ins expected to begin around November 2. Landscaping, final site work, and inspections are all underway as we prepare for occupancy.
We are excited to see the outdoor kitchen pavilion, bocce ball court and putting green installed in the back. It’s a fun new social space for the whole community. Inside, the game room and club room are just about ready for furniture and the exciting golf simulator.
Future residents of the East Brownstone have selected their move in dates and are now getting ready for their move. If you’ve been on the fence about selecting your apartment, now is the time to act.
Contact our team today at Wesley Bradley Park to reserve your apartment.
View our interactive map to see currently available apartments.
Barndt Family Rehabilitation & Care Center

Construction on the Barndt Family Rehabilitation & Care Center is ahead of schedule. The roof is on, and the building is ready for rainy fall weather. The care center is scheduled for completion in August 2027. Enjoy aerial views provided by Walsh Construction Company.
Licensed to provide skilled nursing and long-term care, the new Barndt Family Rehab & Care Center will have private suites for restful recovery from major health events and provide peace of mind for residents and the greater community as availability allows. Offering the full continuum of care on one campus makes it easy for residents and family members to visit loved ones – providing convenience and peace of mind.
Wesley Des Moines: Creekside
Walsh Construction is making great progress and pushing to having all concrete poured by the Thanksgiving holiday. We are finalizing the customization options for those who have reserved apartments and expect to have these selections ready this month. Future residents who sign up before the end of the year are able to choose their color scheme; select flooring and window treatments; upgrade cabinets, countertops and appliances; and add electrical outlets and shower doors. You’ll want to act quickly as the customization window only goes through the end of this year.
30 Apartments Already Reserved
We are off to a great start with 30 apartments already reserved! Our team continues to contact those who have expressed interest in Creekside in order of their priority reservation date to select an apartment.
Reserving apartments in Creekside requires an up-to-date confidential application, Entrance Deposit Agreement and 10% of the Entrance Deposit of which $5,000 is non-refundable.
Captain’s Club members have all had the opportunity to select an apartment, and reservations are now open to those who are not on the waiting list.
About Creekside:
Creekside is a new independent living building planned on the northeast corner of the campus where the former Wesley Des Moines care center is located. With four floors of spacious apartments over a level of enclosed parking, a top-floor club room and exciting new outdoor amenities, this new lifestyle choice will be similar to Wesley’s Brownstone accommodations.
Apartments range from 800 to 1,800 square feet offering One Bedroom, One Bedroom plus Den/Sunroom, Two Bedroom and Two Bedroom plus Den/Sunroom arrangements. Some apartments have a convenient half bath for guests while others feature wrap-around or double decks. Early depositors will have options for upgrades including flooring, countertops, window coverings and appliances.
Wesley Des Moines: The Terrace Renovations

Renovation work on the new Bistro, Dining and the Julia C. Moser Center for the Performing Arts is ahead of schedule and is nearing completion this month. Furniture delivery is expected in October, and the new spaces are set to open in November. The new modern dining room and enhanced bistro will be available to all residents on campus.
The apartment corridors are also getting modern updates: new trim work, paint, carpet, artwork and lighting. Level 2 was the first to be completed. Levels 3, 6 and 1 are well underway with levels 4, 5 and the Leisure Level to follow. Rumor has it the Wesley Community Foundation is spearheading exciting renovations of the spa area on the lower level with a special décor theme.
For a limited time, we are holding Entrance Deposits for The Terrace apartments at 2025 rates. Once construction is finished in The Terrace, these rates will increase.
We still have Alcove and One-Bedroom apartments available for immediate move in. Now is the time to make your move to Wesley Des Moines before the new performing arts center and renovated dining experience are open. Enjoy all the new amenities that this special community has to offer plus award-winning fitness programs and popular Wesley U classes.
Contact our team to let us help you plan your move to Wesley Des Moines!
Wesley Spring Glen
Our development team continues to work with King County for the permit. We have submitted the latest responses back to the County and are hopeful the permit will be issued soon.
Based on permitting, site requirements and financing, the site work required for this building is extensive. We must start in spring to keep from incurring wet weather conditions and costs. We are still working toward a spring 2027 start of construction but there is a possibility it could push to spring 2028. Construction will take approximately 2.5 years.